Date
October 27, 2021 → November 22, 2021
Assign
@ToBeRemoved , @Aayush Rajasekaran
Status
Completed
First-timer
Aayush Rajasekaran
Property
Estimated delivery date, that is still relevant and approved:
- @November 22, 2021 we plan to delivery MVP version of Actors for SnapDeals implementation, which will enable us to start internal and external audits
- This milestone will also include: "Sector key" Milestone: Actors Phase 2 - SectorKey - should be delivered by @November 23, 2021
Relevant issue link from Github:
Relevant PRs:
Dependency PRs:
Definition of done criteria for this milestone:
Validation of snap deals replica update proofs is threaded all the way through from runtime to ffi
The network upgrade logic and a stub for the state migration are in place
lotus compiles consuming the specs-actors v7 module
In other words, this includes stage 1 of "Lotus Actors integration" necessary for the internal audit that will start on the @November 23, 2021
Implementation remarks and notes for this milestone:
- @Aayush Rajasekaran - we can reach the deadline of 22nd without tests, that are done according to Actors standards