Logo

    Implementation Roadmap items

    Q3 Plan
    How much time it will take - estimation
    Man-days estimation
    DRI: Who own this line of work and deliveries
    Comments/Flags
    Current status
    Proof writing

    Aug 25th - October 15th

    ~ 40 days

    @Friedel Ziegelmayer @

    We have 2 big unknowns: 1. Integration of new circuits into the system, we don’t know how that will impact things. 2. Circuit design changes are always tricky.

    In progress
    Actors updates

    August 11th - August 24th

    ~ 11 Days

    @ToBeRemoved

    We can start internal audit of the implementation as soon as we have the actors implementation

    Backlog
    Lotus proofs integration

    August 26th - Sept 3rd

    ~ 5 days

    @

    We can start earlier with mocking and opening the API's, we don’t need to wait for entire proofs implementation to be done

    Backlog
    Lotus actors integration

    Sept 5th - Sept 13th

    ~ 7 days

    @ToBeRemoved @

    Backlog
    Lotus changes to the storage subsystem

    Sept 14th - Sept 24rd

    ~ 5 days

    @Magik6k we need to help with this

    It will take 5-7 days for @ or @ToBeRemoved to do it. Would be a great Knowledge sharing opportunity.

    Backlog
    Write tests and validate the implementation - Actors

    September 24th - October 1st

    ~ 5 days

    @ToBeRemoved

    Backlog
    Write tests and validate the implementation - Lotus

    October 1st - October 15th

    ~ 10 days

    @

    Backlog
    Gas estimation for Proof verification

    October 15th - October 21st

    ~ 4 days

    @

    Backlog
    Audit (internal + external)

    October 10th - November 10th

    ~ 20 days

    @Friedel Ziegelmayer + @Nicola for the internal audit, @ to TPM the Circuits audit with external vendors(J.P.)

    We can start the audit as soon as we have the proofs writing done

    Ongoing discussion
    Organize participants for trusted setup

    October 29rd - November 7th

    ~ 7 days

    @ @jennijuju

    Backlog
    Trusted Setup

    November 10th -December 17th

    ~ 25 days

    @ + development team representative

    We would need new parameter files, which will generate new snarks. There is a possibility that we can start circuits trusted setup before the planned timeline. We would need approval from all side that we should do this - we freeze the circuits and start setup on that part

    Ongoing discussion
    Testnet validations, hot fixes and delivery of final Release candidate

    December 20th - January 15th 2022

    ~ 20 days

    @, @ToBeRemoved

    Backlog
    Network upgrade + support

    January 15th 2022 - 5th of February 2022

    ~ 15 days

    @jennijuju @

    since we need to make good on our promises for Exchanges and Miners - 2 weeks of notice period

    Backlog

    SUM: 167 Man-Days

    CryptoNet is a Protocol Labs initiative.