Q1/Q2 Plan | ETA | Date | Dependency | Effort | DRI | Comments/Flags | Current status |
---|---|---|---|---|---|---|---|
Req gathering and Proof updates | 3-4w | February 21, 2023 | Lotus | TBD | FilCrypto/nemo | Backlog | |
Write tests and validate the implementation - Proofs | 1w | TBD | FilCrypto/CNL | Backlog | |||
Filecoin Proofs API and FFI updates | 1w | TBD | FilCrypto/nemo | ||||
Actors updates | 1w | TBD | TBD | Backlog | |||
Write tests and validate the implementation - Actors | 3d | TBD | TBD | Backlog | |||
Lotus proofs integration | 1w | TBD | TBD | Backlog | |||
Lotus actors integration | 2d | TBD | Backlog | ||||
Write tests and validate the implementation - Lotus | 3d | TBD | TBD | Backlog | |||
Gas estimation for Proof verification | 5d (if test vectors are available) | TBD | TBD | Challenge generation changes the verification performance carachteristics | Backlog | ||
Audit (internal only) | 1w | TBD | TBD | We can start the audit as soon as we have the proofs updates done | Backlog | ||
Testnet validations, hot fixes and delivery of final Release candidate | 1w | TBD | TBD | Backlog | |||
Network upgrade + support | 2w | TBD | TBD | Backlog |