Created
Feb 28, 2022 2:59 PM
Reporter
Dragan Zurzin
Current Project Delivery status is:
🟢 Green - We are on the right path to deliver the Project
- Risk factors that need to be included: - that can potentially change our green status:
- The trusted setup schedule looks good, for now, but maybe we will not do all participants until @December 20, 2021 as was the original plan.
It will potentially take extra 2 days for us to close the internal trusted setup.
Expected ship date: 2022-02-20
Status explained:
- We successfully passed External Audit with JP Aumasson - @November 26, 2021
Findings of the audit are shared on our related Milestone page.
- In the following week - We will focus on running the Internal trusted setup for PL participants - The event calendar is available here
How do we keep the 🟢 Green status in the next 2 weeks:
- We successfully run params Internal (PL) Trusted setup until @December 21, 2021 for all planned participants
- We organize all the infra logistics for External trusted setup
- We approve all the External Participants + get the final schedule shared after the next core devs call
Notice: Statuses above are based on the following definition/rule
Delivery timeline snapshot:
- Get a full overview of the timeline by visiting this page: SnapDeals Timeline
Important delivery dates for this and the following week:
- @December 20, 2021 - Start running Actors and Lotus codebase on Calibration net, related to SnapDeals updates we made
- @December 21, 2021 - Share final participant list and create communication channels for all participants in the external trusted setup
- @December 22, 2021 - Finish Internal run for trusted setup
Current development tasks - In Progress items:
- Changes + redesign of sector-storage that are needed to support SnapDeal
- FSM changes that we need to make for Snapdeals implementation -
- Actors Testing -
- Lotus Testing -
Recent wins/accomplishments:
- We successfully passed all the audit items from the external audit with JP for this implementation - @December 8, 2021
- We started running params for our internal trusted setup - @December 9, 2021
- We booked over half of the participants for the external trusted setup, we will close the entire cycle before the holiday's session - @December 15, 2021
"Read more" and useful links:
- https://github.com/orgs/filecoin-project/projects/17 - SnapDeal development board
- SnapDeals Index page with relevant links - index page with all the major links connected to this project